Dept. of Trans. PROGRESS Serial No. Contract No. 15-055-07-22 07-260704 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 58% Location: Federal Project: 07-VEN-101-R39.8/R43.6 NONE Progress payment No. 036 Payment period ending: 02-20-15 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,117,050.61 837,592.32 2. a. Extra Work 5,549,255.63 158,637.31 b. Adustment Comp. 54,059.82 -225,828.05 3. Materials on Hand 0.00 -4,000.00 4. Earned Subject to Retention 50,720,366.06 766,401.58 5. Mobilization 4,664,165.39 0.00 6. Total Work Completed 55,384,531.45 7. Deductions -231.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 55,384,300.45 766,401.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 766,401.58