Dept. of Trans. PROGRESS Serial No. Contract No. 11-082-11-12 07-260904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 75% 07-LA-405-7.6/9.3 Federal Project: NONE Progress payment No. 04 Payment period ending: 03-20-11 POWELL CONSTRUCTORS INC 8555 BANANA AVENUE FONTANCA, CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 88,412.68 34,859.18 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 88,412.68 34,859.18 5. Mobilization 19,000.00 4,000.00 6. Total Work Completed 107,412.68 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 107,412.68 38,859.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,859.18