Dept. of Trans. PROGRESS Serial No. Contract No. 14-267-08-06 07-265904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 80% 07-LA-101-1.0/11.0 Federal Project: ACNH-P101(227) Progress payment No. 07 Payment period ending: 09-20-14 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 460,396.66 56,850.00 2.a. Extra Work 92,889.78 61,531.92 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 553,286.44 118,381.92 5. Mobilization 152,000.00 32,000.00 6. Total Work Completed 705,286.44 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -11,838.19 -11,838.19 c. Reduction after 95% Comp. 9. Total pay to Contractor 693,448.25 138,543.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 138,543.73