Dept. of Trans. PROGRESS Serial No. Contract No. 13-325-15-27 07-266104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 12% 45% 07-LA-134-0.0/13.3 Federal Project: HSNH-P134(36) Progress payment No. 05 Payment period ending: 11-20-13 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 303,948.59 155,887.29 2.a. Extra Work 1,075.64 1,075.64 b. Adjustment Comp. 3. Materials on Hand 107,976.59 59,621.03 4. Earned Subject to Retention 413,000.82 216,583.96 5. Mobilization 90,000.00 30,000.00 6. Total Work Completed 395,024.23 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 503,000.82 246,583.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 246,583.96