Dept. of Trans. PROGRESS Serial No. Contract No. 12-265-12-57 07-269004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 98% 07-LA-710-18.1/20.8 Federal Project: SARR-P710(14) A-P710(14) Progress payment No. 35 Payment period ending: 09-20-12 SEMA CONSTRUCTION INC 6 ORCHARD SUITE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,689,618.51 12,350.00 2.a. Extra Work 2,742,969.02 70,125.99 b. Adjustment Comp. 1,000,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 37,432,587.53 82,475.99 5. Mobilization 2,420,000.00 0.00 6. Total Work Completed 39,852,587.53 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 39,852,587.53 82,475.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,475.99