Dept. of Trans. FINAL Serial No. Contract No. 14-111-08-58 07-269004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-710-18.1/20.8 Federal Project: SARR-P710(14) A-P710(14) Progress payment No. 43 Payment period ending: 01-21-13 SEMA CONSTRUCTION INC 320 GODDARD WAY, SUITE 150 IRVINE, CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,611,015.13 0.00 2.a. Extra Work 3,281,135.18 0.00 b. Adjustment Comp. 3,707,130.88 530,344.90 3. Materials on Hand 4. Earned Subject to Retention 40,599,281.19 530,344.90 5. Mobilization 2,420,000.00 0.00 6. Total Work Completed 43,019,281.19 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 43,019,281.19 530,344.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 530,344.90