Dept. of Trans. FINAL Serial No. Contract No. 16-068-15-09 07-273104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-110-9.8/14.0 STP-X037(166) Progress payment No. 007 Payment period ending: 03-26-15 HIGHLAND CONSTRUCTION INC 133 N PIXLEY ST ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,300.00 0.00 2. a. Extra Work 4,366.54 0.00 b. Adustment Comp. 473,090.78 209,500.00 3. Materials on Hand 4. Earned Subject to Retention 481,757.32 209,500.00 5. Mobilization 100,000.00 0.00 6. Total Work Completed 581,757.32 7. Deductions -100,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 481,757.32 209,500.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 209,500.00