Dept. of Trans. PROGRESS Serial No. Contract No. 14-147-09-24 07-2759U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 59% 07-LA-110-R23.5/R23.9 Federal Project: NHP-X037(164) Progress payment No. 04 Payment period ending: 05-20-14 YAKAR 113 E ARROW HIGHWAY SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 454,468.75 189,448.30 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 454,468.75 189,448.30 5. Mobilization 79,800.00 0.00 6. Total Work Completed 534,268.75 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 534,268.75 189,448.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 189,448.30