Dept. of Trans. PROGRESS Serial No. Contract No. 14-267-10-30 07-2759U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 88% 07-LA-110-R23.5/R23.9 Federal Project: NHP-X037(164) Progress payment No. 08 Payment period ending: 09-20-14 YAKAR 113 E ARROW HIGHWAY SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 775,452.00 47,954.40 2.a. Extra Work 14,005.85 14,005.85 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 789,457.85 61,960.25 5. Mobilization 84,000.00 0.00 6. Total Work Completed 873,457.85 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 873,457.85 61,960.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 61,960.25