Dept. of Trans. PROGRESS Serial No. Contract No. 13-294-14-58 07-2769U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 57% 07-LA-170-17.7/20.3 Federal Project: NH-P170(4) Progress payment No. 05 Payment period ending: 10-20-13 Y A K A R 113 E ARROW HIGHWAY SAN DIMAS CA 91733 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 261,797.75 70,283.00 2.a. Extra Work 33,015.54 33,015.54 b. Adjustment Comp. 41,581.83 41,581.83 3. Materials on Hand 4. Earned Subject to Retention 336,395.12 144,880.37 5. Mobilization 64,600.00 13,600.00 6. Total Work Completed 400,995.12 7. Deductions -9,000.00 -9,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 391,995.12 149,480.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 149,480.37