Dept. of Trans. PROGRESS Serial No. Contract No. 14-023-15-14 07-2769U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 87% 07-LA-170-17.7/20.3 Federal Project: NH-P170(4) Progress payment No. 08 Payment period ending: 01-20-14 Y A K A R 113 E ARROW HIGHWAY SAN DIMAS CA 91733 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 600,562.50 129,441.95 2.a. Extra Work 140,910.32 29,609.08 b. Adjustment Comp. 116,429.12 18,711.82 3. Materials on Hand 4. Earned Subject to Retention 857,901.94 177,762.85 5. Mobilization 68,000.00 3,400.00 6. Total Work Completed 925,901.94 7. Deductions 0.00 3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 925,901.94 184,162.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 184,162.85