Dept. of Trans. PROGRESS Serial No. Contract No. 13-326-08-57 07-2770U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 100% 07-LA-118-11.5/13.7 Federal Project: NH-P118(63) Progress payment No. 08 Payment period ending: 11-20-13 CLEAN CUT LANDSCAPE 8406 N ARMSTRONG AVE CLOVIS CA 93619 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 890,263.47 145,124.52 2.a. Extra Work 35,031.88 1,520.23 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 925,295.35 146,644.75 5. Mobilization 32,264.00 0.00 6. Total Work Completed 957,559.35 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -75,731.03 -14,664.48 c. Reduction after 95% Comp. 9. Total pay to Contractor 881,828.32 131,980.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 131,980.27