Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-13-11 07-278204 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 88% Location: Federal Project: 07-LA-10-18.3/46.8 STP-X037(167) Progress payment No. 003 Payment period ending: 03-20-15 STL LANDSCAPE INC 8122 COMPTON AVE LOS ANGELES CA 90001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 103,476.71 46,558.91 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 103,476.71 46,558.91 5. Mobilization 36,411.75 12,137.25 6. Total Work Completed 139,888.46 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -4,655.89 -4,655.89 c. Reduction after 95% Comp. 9. Total pay to Contractor 135,232.57 54,040.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 54,040.27