Dept. of Trans. PROGRESS Serial No. Contract No. 14-147-08-51 07-278304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 21% 07-LA-405-3.4/4.5 Federal Project: NHPI-4053(34) Progress payment No. 06 Payment period ending: 05-20-14 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 301,497.65 43,300.00 2.a. Extra Work 102,400.62 102,400.62 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 403,898.27 145,700.62 5. Mobilization 175,898.25 0.00 6. Total Work Completed 579,796.52 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 579,796.52 145,700.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 145,700.62