Dept. of Trans. PROGRESS Serial No. Contract No. 17-081-12-57 07-279114 PROGRESS PAYMENT VOUCHER %complete: %time: 4% 7% Location: Federal Project: 07-LA-60-R24.4/R25.3 TTDG-6204(76) Progress payment No. 004 Payment period ending: 03-20-17 ORTIZ ENTERPRISES INC 6 CUSHING #200 IRVINE CA 926184221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 535,309.05 129,527.49 2. a. Extra Work 6,600.06 6,600.06 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 541,909.11 136,127.55 5. Mobilization 6. Total Work Completed 541,909.11 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 541,909.11 136,127.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,127.55