Dept. of Trans. PROGRESS Serial No. Contract No. 18-054-18-31 07-279114 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 41% Location: Federal Project: 07-LA-60-R24.4/R25.3 TTDG-6204(76) Progress payment No. 015 Payment period ending: 02-20-18 ORTIZ ENTERPRISES INC 6 CUSHING #200 IRVINE CA 926184221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,582,213.31 989,593.87 2. a. Extra Work 229,173.76 23,197.15 b. Adustment Comp. 338,776.81 23,112.83 3. Materials on Hand 98,014.93 0.00 4. Earned Subject to Retention 11,248,178.81 1,035,903.85 5. Mobilization 1,350,000.00 0.00 6. Total Work Completed 12,500,163.88 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,598,178.81 1,036,903.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,036,903.85