Dept. of Trans. PROGRESS Serial No. Contract No. 11-112-14-38 07-279404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 52% 07-LA-5-15.3/17.2 Federal Project: NONE Progress payment No. 05 Payment period ending: 04-20-11 HIGHLAND CONSTRUCTION INC 133 N PIXLEY STREET ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 442,163.04 24,633.74 2.a. Extra Work 19,328.72 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 461,491.76 24,633.74 5. Mobilization 10,000.00 0.00 6. Total Work Completed 471,491.76 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 471,491.76 24,633.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,633.74