Dept. of Trans. PROGRESS Serial No. Contract No. 13-053-13-45 07-279804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 26% 07-LA-10-20.4/21.5 Federal Project: NONE Progress payment No. 05 Payment period ending: 02-20-13 WESTCOAST PUBLIC WORK INC 20058 VENTURA BOULEVARD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 644,324.96 220,480.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 644,324.96 220,480.90 5. Mobilization 117,481.00 5,874.05 6. Total Work Completed 761,805.96 7. Deductions -9,489.20 -474.46 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 752,316.76 225,880.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 225,880.49