Dept. of Trans. PROGRESS Serial No. Contract No. 17-116-11-51 07-2827U4 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 33% Location: Federal Project: 07-LA-101-S0.0/25.9 NHP-X037(192) Progress payment No. 009 Payment period ending: 04-20-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,156,683.47 710,714.06 2. a. Extra Work 70,142.76 0.00 b. Adustment Comp. 3. Materials on Hand 419,756.47 -843.37 4. Earned Subject to Retention 3,646,582.70 709,870.69 5. Mobilization 665,000.00 0.00 6. Total Work Completed 3,891,826.23 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,311,582.70 709,870.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 709,870.69