Dept. of Trans. PROGRESS Serial No. Contract No. 17-234-09-59 07-2827U4 PROGRESS PAYMENT VOUCHER %complete: %time: 47% 43% Location: Federal Project: 07-LA-101-S0.0/25.9 NHP-X037(192) Progress payment No. 013 Payment period ending: 08-20-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,793,762.07 321,565.56 2. a. Extra Work 332,779.86 699.33 b. Adustment Comp. 3. Materials on Hand 510,191.62 -9,953.72 4. Earned Subject to Retention 5,636,733.55 312,311.17 5. Mobilization 665,000.00 0.00 6. Total Work Completed 5,791,541.93 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,301,733.55 313,311.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 313,311.17