Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-13-44 07-2827U4 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 48% Location: Federal Project: 07-LA-101-S0.0/25.9 NHP-X037(192) Progress payment No. 014 Payment period ending: 09-20-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,116,857.09 323,095.01 2. a. Extra Work 391,009.00 58,229.14 b. Adustment Comp. 3. Materials on Hand 507,108.13 -3,083.49 4. Earned Subject to Retention 6,014,974.22 378,240.66 5. Mobilization 700,000.00 35,000.00 6. Total Work Completed 6,207,866.09 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,714,974.22 413,240.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 413,240.66