Dept. of Trans. PROGRESS Serial No. Contract No. 17-296-12-59 07-2827U4 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 53% Location: Federal Project: 07-LA-101-S0.0/25.9 NHP-X037(192) Progress payment No. 015 Payment period ending: 10-20-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,391,125.22 274,268.13 2. a. Extra Work 385,020.59 -5,988.41 b. Adustment Comp. 3. Materials on Hand 489,226.56 -17,881.57 4. Earned Subject to Retention 6,265,372.37 250,398.15 5. Mobilization 700,000.00 0.00 6. Total Work Completed 6,476,145.81 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,965,372.37 250,398.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 250,398.15