Dept. of Trans. PROGRESS Serial No. Contract No. 17-332-07-44 07-2827U4 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 52% Location: Federal Project: 07-LA-101-S0.0/25.9 NHP-X037(192) Progress payment No. 016 Payment period ending: 11-20-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,522,164.00 131,038.78 2. a. Extra Work 605,493.20 220,472.61 b. Adustment Comp. 3. Materials on Hand 483,446.38 -5,780.18 4. Earned Subject to Retention 6,611,103.58 345,731.21 5. Mobilization 700,000.00 0.00 6. Total Work Completed 6,827,657.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,311,103.58 345,731.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 345,731.21