Dept. of Trans. PROGRESS Serial No. Contract No. 18-085-12-29 07-2827U4 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 54% Location: Federal Project: 07-LA-101-S0.0/25.9 NHP-X037(192) Progress payment No. 020 Payment period ending: 03-20-18 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,248,462.56 199,524.74 2. a. Extra Work 809,208.28 24,914.56 b. Adustment Comp. 3. Materials on Hand 430,015.03 -29,091.13 4. Earned Subject to Retention 7,487,685.87 195,348.17 5. Mobilization 700,000.00 0.00 6. Total Work Completed 7,757,670.84 7. Deductions 0.00 11,138.73 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,187,685.87 206,486.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 206,486.90