Dept. of Trans. PROGRESS Serial No. Contract No. 18-204-14-56 07-2827U4 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 53% Location: Federal Project: 07-LA-101-S0.0/25.9 NHP-X037(192) Progress payment No. 024 Payment period ending: 07-20-18 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,065,272.21 248,149.18 2. a. Extra Work 861,736.49 22,137.45 b. Adustment Comp. 3. Materials on Hand 260,480.60 -15,214.48 4. Earned Subject to Retention 8,187,489.30 255,072.15 5. Mobilization 700,000.00 0.00 6. Total Work Completed 8,627,008.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,887,489.30 255,072.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 255,072.15