Dept. of Trans. PROGRESS Serial No. Contract No. 19-169-15-15 07-2827U4 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 53% Location: Federal Project: 07-LA-101-S0.0/25.9 NHP-X037(192) Progress payment No. 035 Payment period ending: 06-20-19 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,339,385.67 855,252.00 2. a. Extra Work 1,359,102.44 0.00 b. Adustment Comp. -704,162.94 -713,902.13 3. Materials on Hand 27,121.27 -124,027.01 4. Earned Subject to Retention 9,021,446.44 17,322.86 5. Mobilization 700,000.00 0.00 6. Total Work Completed 9,694,325.17 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,721,446.44 17,322.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,322.86