Dept. of Trans. PROGRESS Serial No. Contract No. 19-205-10-48 07-2827U4 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 53% Location: Federal Project: 07-LA-101-S0.0/25.9 NHP-X037(192) Progress payment No. 036 Payment period ending: 07-20-19 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,468,475.67 129,090.00 2. a. Extra Work 1,361,386.26 2,283.82 b. Adustment Comp. -704,162.94 0.00 3. Materials on Hand 0.00 -27,121.27 4. Earned Subject to Retention 9,125,698.99 104,252.55 5. Mobilization 700,000.00 0.00 6. Total Work Completed 9,825,698.99 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,825,698.99 104,252.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 104,252.55