Dept. of Trans. PROGRESS Serial No. Contract No. 15-054-13-57 07-284204 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 25% Location: Federal Project: 07-LA-5-18.2/26.7 STPE-005(93) Progress payment No. 004 Payment period ending: 02-20-15 Y A K A R 689 EAST SAN BERNARDINO ROAD COVINA, CA 91723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 212,288.80 147,542.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 30,881.58 30,881.58 4. Earned Subject to Retention 243,170.38 178,424.38 5. Mobilization 25,555.00 5,380.00 6. Total Work Completed 237,843.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 268,725.38 183,804.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 183,804.38