Dept. of Trans. PROGRESS Serial No. Contract No. 15-026-12-41 07-284504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 86% 07-LA-14-R56.5/R57.0 Federal Project: STP-P014(73) Progress payment No. 04 Payment period ending: 01-20-15 STL LANDSCAPE INC 8122 COMPTON AVE LOS ANGELES CA 90001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 108,730.00 37,445.00 2.a. Extra Work b. Adjustment Comp. 24,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 132,730.00 37,445.00 5. Mobilization 25,521.75 5,373.00 6. Total Work Completed 158,251.75 7. Deductions -3,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 155,251.75 42,818.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,818.00