Dept. of Trans. PROGRESS Serial No. Contract No. 16-207-12-34 07-287104 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 18% Location: Federal Project: 07-LA-101-0.0/0.1 HSNH-PG Q101-280(E) Progress payment No. 006 Payment period ending: 07-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 292,379.62 34,374.00 2. a. Extra Work 26,731.19 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 319,110.81 34,374.00 5. Mobilization 103,500.00 0.00 6. Total Work Completed 422,610.81 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 422,610.81 34,374.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,374.00