Dept. of Trans. PROGRESS Serial No. Contract No. 15-236-14-33 07-287204 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 88% Location: Federal Project: 07-LA-134-1.6/2.7 NHP-P134(37) Progress payment No. 007 Payment period ending: 08-20-15 MARTINEZ LANDSCAPE CO., INC. 12357 SAN FERNANDO ROAD SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 791,526.35 229,188.25 2. a. Extra Work 3,988.63 679.68 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 795,514.98 229,867.93 5. Mobilization 55,000.00 0.00 6. Total Work Completed 850,514.98 7. Deductions -3,000.00 7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 847,514.98 236,867.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 236,867.93