Dept. of Trans. PROGRESS Serial No. Contract No. 15-324-09-56 07-287304 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 17% Location: Federal Project: 07-LA-210-39.8/42.2 NHPI-210-1(824) Progress payment No. 008 Payment period ending: 11-20-15 YAKAR 689 EAST SAN BERNARDINO RD COVINA CA 91723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 635,894.25 112,220.25 2. a. Extra Work 22,500.00 0.00 b. Adustment Comp. 3. Materials on Hand 90,222.50 0.00 4. Earned Subject to Retention 748,616.75 112,220.25 5. Mobilization 56,000.00 2,800.00 6. Total Work Completed 714,394.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 804,616.75 115,020.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,020.25