Dept. of Trans. PROGRESS Serial No. Contract No. 15-355-12-02 07-287304 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 19% Location: Federal Project: 07-LA-210-39.8/42.2 NHPI-210-1(824) Progress payment No. 009 Payment period ending: 12-20-15 YAKAR 689 EAST SAN BERNARDINO RD COVINA CA 91723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 740,927.75 105,033.50 2. a. Extra Work 40,750.00 18,250.00 b. Adustment Comp. 39,825.00 39,825.00 3. Materials on Hand 70,535.00 -19,687.50 4. Earned Subject to Retention 892,037.75 143,421.00 5. Mobilization 56,000.00 0.00 6. Total Work Completed 877,502.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 948,037.75 143,421.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 143,421.00