Dept. of Trans. PROGRESS Serial No. Contract No. 16-236-12-37 07-287404 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 26% Location: Federal Project: 07-LA-405-8.7/11.2 HSNH-PIG 405-2(976) Progress payment No. 006 Payment period ending: 08-20-16 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 882,863.70 188,869.90 2. a. Extra Work 18,718.67 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 901,582.37 188,869.90 5. Mobilization 128,250.00 0.00 6. Total Work Completed 1,029,832.37 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,029,832.37 188,869.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 188,869.90