Dept. of Trans. PROGRESS Serial No. Contract No. 16-207-12-35 07-287604 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 4% Location: Federal Project: 07-LA-101-8.5/9.5 HSNH-PG Q101-279(E) Progress payment No. 001 Payment period ending: 07-20-16 HIGHLAND CONSTRUCTION INC 133 N PIXLEY ST ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 154,355.50 154,355.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 154,355.50 154,355.50 5. Mobilization 112,500.00 112,500.00 6. Total Work Completed 266,855.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 266,855.50 266,855.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 266,855.50