Dept. of Trans. PROGRESS Serial No. Contract No. 15-026-12-42 07-288014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 42% 07-LA-210-R9.7/R16.1 Federal Project: NHPI-2101(816) Progress payment No. 14 Payment period ending: 01-20-15 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,147,956.37 613,426.79 2.a. Extra Work 154,542.18 0.00 b. Adjustment Comp. 3. Materials on Hand 164,671.00 164,671.00 4. Earned Subject to Retention 16,467,169.55 778,097.79 5. Mobilization 1,489,600.00 0.00 6. Total Work Completed 17,792,098.55 7. Deductions -1,100.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,955,669.55 783,097.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 783,097.79