Dept. of Trans. PROGRESS Serial No. Contract No. 15-295-14-06 07-288014 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 77% Location: Federal Project: 07-LA-210-R9.7/R16.1 NHPI-2101(816) Progress payment No. 024 Payment period ending: 10-20-15 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,006,298.90 998,247.93 2. a. Extra Work 466,896.67 111,626.39 b. Adustment Comp. 53,654.74 18,689.34 3. Materials on Hand 77,256.18 -17,573.02 4. Earned Subject to Retention 31,604,106.49 1,110,990.64 5. Mobilization 1,568,000.00 0.00 6. Total Work Completed 33,094,850.31 7. Deductions -1,100.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 33,171,006.49 1,120,990.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,120,990.64