Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 16-158-11-39 07-2881U4 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 28% Location: Federal Project: 07-LA-210-R16.1/R25.8 NHPI-210-1(823) Progress payment No. 014 Payment period ending: 05-20-16 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,610,722.80 355,250.00 2. a. Extra Work 335,350.77 0.00 b. Adustment Comp. 622,710.56 0.00 3. Materials on Hand 3,429,951.51 0.00 4. Earned Subject to Retention 23,998,735.64 355,250.00 5. Mobilization 7,600,000.00 0.00 6. Total Work Completed 28,168,784.13 7. Deductions -6,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,592,735.64 355,250.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 355,250.00