Dept. of Trans. PROGRESS Serial No. Contract No. 18-297-10-01 07-2881U4 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 72% Location: Federal Project: 07-LA-210-R16.1/R25.8 NHPI-210-1(823) Progress payment No. 044 Payment period ending: 10-20-18 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 89,788,493.86 383,184.84 2. a. Extra Work 7,758,831.88 1,670,748.05 b. Adustment Comp. 5,627,394.77 548,321.37 3. Materials on Hand 421,178.87 -160,881.29 4. Earned Subject to Retention 103,595,899.38 2,441,372.97 5. Mobilization 8,000,000.00 0.00 6. Total Work Completed 111,174,720.51 7. Deductions -193,100.00 6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 111,402,799.38 2,447,372.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,447,372.97