Dept. of Trans. PROGRESS Serial No. Contract No. 22-054-13-59 07-289104 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 76% Location: Federal Project: 07-LA-405-11.9/13.2 NONE Progress payment No. 028 Payment period ending: 02-20-22 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,584,874.10 0.00 2. a. Extra Work 105,646.35 14,414.57 b. Adustment Comp. 316,126.69 0.00 3. Materials on Hand 179,945.04 0.00 4. Earned Subject to Retention 7,186,592.18 14,414.57 5. Mobilization 600,000.00 0.00 6. Total Work Completed 7,606,647.14 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,776,592.18 4,414.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,414.57