Dept. of Trans. PROGRESS Serial No. Contract No. 16-236-07-56 07-290004 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 11% Location: Federal Project: 07-LA-405-R12.6/R21.2 NHPI-405 2-977(E) Progress payment No. 004 Payment period ending: 08-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 261,776.10 32,306.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 49,237.76 0.00 4. Earned Subject to Retention 311,013.86 32,306.10 5. Mobilization 6. Total Work Completed 261,776.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 311,013.86 32,306.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,306.10