Dept. of Trans. PROGRESS Serial No. Contract No. 18-023-15-26 07-290004 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 49% Location: Federal Project: 07-LA-405-R12.6/R21.2 NHPI-405 2-977(E) Progress payment No. 022 Payment period ending: 01-20-18 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,681,521.67 140,605.00 2. a. Extra Work 122,990.06 9,556.97 b. Adustment Comp. 3. Materials on Hand 368,840.04 15,203.60 4. Earned Subject to Retention 6,173,351.77 165,365.57 5. Mobilization 95,000.00 0.00 6. Total Work Completed 5,899,511.73 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,258,351.77 155,365.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 155,365.57