Dept. of Trans. PROGRESS Serial No. Contract No. 19-169-11-25 07-290004 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 99% Location: Federal Project: 07-LA-405-R12.6/R21.2 NHPI-405 2-977(E) Progress payment No. 040 Payment period ending: 06-20-19 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,380,855.76 478,343.39 2. a. Extra Work 297,821.03 6,285.75 b. Adustment Comp. 3. Materials on Hand 203,329.35 -165,510.19 4. Earned Subject to Retention 11,882,006.14 319,118.95 5. Mobilization 100,000.00 0.00 6. Total Work Completed 11,778,676.79 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,982,006.14 319,118.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 319,118.95