Dept. of Trans. PROGRESS Serial No. Contract No. 18-082-15-05 07-290104 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 56% Location: Federal Project: 07-LA-91-6.5/11.0 HSNH-PG X037-184(E) Progress payment No. 021 Payment period ending: 03-20-18 AUTOBAHN CONSTRUCTION, INC 933 N. BATAVIA ST ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,975,563.40 111,357.20 2. a. Extra Work 747,564.15 56,360.89 b. Adustment Comp. 30,022.03 30,022.03 3. Materials on Hand 111,235.76 -113,272.38 4. Earned Subject to Retention 6,864,385.34 84,467.74 5. Mobilization 420,000.00 0.00 6. Total Work Completed 7,173,149.58 7. Deductions -6,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,278,385.34 84,467.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 84,467.74