Dept. of Trans. PROGRESS Serial No. Contract No. 17-332-09-20 07-290404 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 59% Location: Federal Project: 07-VEN-101-29.8/29.8 NONE Progress payment No. 003 Payment period ending: 11-20-17 GUILLS INC 313 E ORANGE GROVE BLVD 290 PASADENA CA 91104 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 241,568.16 124,572.45 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 241,568.16 124,572.45 5. Mobilization 34,000.00 1,700.00 6. Total Work Completed 275,568.16 7. Deductions -1,442.26 -72.12 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 274,125.90 126,200.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 126,200.33