Dept. of Trans. PROGRESS Serial No. Contract No. 16-264-15-06 07-290704 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 0% Location: Federal Project: 07-LA-47-0.9/2.0 NHP-P047(11) Progress payment No. 002 Payment period ending: 09-20-16 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 241,200.00 238,300.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 42,856.71 0.00 4. Earned Subject to Retention 284,056.71 238,300.00 5. Mobilization 6. Total Work Completed 241,200.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 284,056.71 238,300.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 238,300.00