Dept. of Trans. PROGRESS Serial No. Contract No. 17-332-09-29 07-290804 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 40% Location: Federal Project: 07-LA-1-2.7/12.1 ACST-PP00-1(616) Progress payment No. 005 Payment period ending: 11-20-17 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,139,683.04 744,588.84 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 107,266.32 0.00 4. Earned Subject to Retention 1,246,949.36 744,588.84 5. Mobilization 125,000.00 6,250.00 6. Total Work Completed 1,264,683.04 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,371,949.36 750,838.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 750,838.84