Dept. of Trans. FINAL Serial No. Contract No. 15-138-15-09 07-290904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-210-R6.8/R7.2 HPIG-2101(818) Progress payment No. 008 Payment period ending: 07-21-14 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 621,906.00 0.00 2. a. Extra Work 42,612.55 0.00 b. Adustment Comp. 130,000.00 130,000.00 3. Materials on Hand 4. Earned Subject to Retention 794,518.55 130,000.00 5. Mobilization 85,000.00 0.00 6. Total Work Completed 879,518.55 7. Deductions 0.00 58,900.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 879,518.55 188,900.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 188,900.00