Dept. of Trans. PROGRESS Serial No. Contract No. 18-171-14-33 07-291104 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 52% Location: Federal Project: 07-LA-101-30.9/38.2 ACNH-X037(200) Progress payment No. 003 Payment period ending: 06-20-18 STL LANDSCAPE INC 8122 COMPTON AVE LOS ANGELES CA 90001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 216,195.62 146,351.62 2. a. Extra Work 20,203.36 20,203.36 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 236,398.98 166,554.98 5. Mobilization 71,250.00 23,750.00 6. Total Work Completed 307,648.98 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 307,648.98 190,304.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 190,304.98