Dept. of Trans. PROGRESS Serial No. Contract No. 19-168-17-35 07-291204 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 49% Location: Federal Project: 07-LA-57-R7.7/R12.2 NONE Progress payment No. 007 Payment period ending: 06-20-19 HIGHLAND CONSTRUCTION INC 133 N PIXLEY ST ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 719,726.03 18,686.40 2. a. Extra Work 92,073.31 52,929.42 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 811,799.34 71,615.82 5. Mobilization 45,100.00 0.00 6. Total Work Completed 856,899.34 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 856,899.34 73,615.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 73,615.82